www.sefindia.org

STRUCTURAL ENGINEERING FORUM OF INDIA [SEFI]

 Forum SubscriptionsSubscriptions DigestDigest Preferences   FAQFAQ   SearchSearch   MemberlistMemberlist   UsergroupsUsergroups  RegisterRegister FAQSecurity Tips FAQDonate
 ProfileProfile   Log in to check your private messagesLog in to check your private messages   Log in to websiteLog in to websiteLog in to websiteLog in to forum 
Warning: Make sure you scan the downloaded attachment with updated antivirus tools  before opening them. They may contain viruses.
Use online scanners
here and here to upload downloaded attachment to check for safety.

Earth work excavation with an initial lead up to 1km. and al

 
Post new topicReply to topic Thank Post    www.sefindia.org Forum Index -> SEFI Web Site Problems/ Login/Registration Issues
View previous topic :: View next topic  
Author Message
anand_kumar
SEFI Member
SEFI Member


Joined: 02 May 2011
Posts: 3

PostPosted: Tue Jul 12, 2011 2:30 am    Post subject: Earth work excavation with an initial lead up to 1km. and al Reply with quote

what is the meaning of "Earth work excavation with an initial lead up to 1km. and all lifts". as given in standard schedule of rates
Back to top
View user's profile Send private message
B.V.Harsoda
Bronze Sponsor
Bronze Sponsor


Joined: 19 Jan 2009
Posts: 2293
Location: RAJKOT,GUJARAT, INDIA

PostPosted: Tue Jul 12, 2011 3:42 am    Post subject: Reply with quote

Lead 1 km means exavated stuff shall be used or disposed up to 1 km.

All lift means rate for all depth what  ever it may be.No different rate shall be paid for

different depth i.e. 1 mt., 2 mt. 3 mt. & so on
Back to top
View user's profile Send private message
atul_123
...
...


Joined: 29 May 2009
Posts: 369
Location: VADODARA, GUJARAT, INDIA.

PostPosted: Wed Jul 13, 2011 6:35 am    Post subject: Reply with quote

B.V.Harsoda wrote:
Lead 1 km means exavated stuff shall be used or disposed up to 1 km.

All lift means rate for all depth what  ever it may be.No different rate shall be paid for

different depth i.e. 1 mt., 2 mt. 3 mt. & so on



very good explanation....
Back to top
View user's profile Send private message
Display posts from previous:   
Post new topicReply to topic Thank Post    www.sefindia.org Forum Index -> SEFI Web Site Problems/ Login/Registration Issues All times are GMT
Page 1 of 1

 

 
Jump to:  
You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot vote in polls in this forum
You cannot attach files in this forum
You cannot download files in this forum


© 2003, 2008 SEFINDIA, Indian Domain Registration
Publishing or acceptance of an advertisement is neither a guarantee nor endorsement of the advertiser's product or service. advertisement policy