www.sefindia.org

STRUCTURAL ENGINEERING FORUM OF INDIA [SEFI]

 Forum SubscriptionsSubscriptions DigestDigest Preferences   FAQFAQ   SearchSearch   MemberlistMemberlist   UsergroupsUsergroups  RegisterRegister FAQSecurity Tips FAQDonate
 ProfileProfile   Log in to check your private messagesLog in to check your private messages   Log in to websiteLog in to websiteLog in to websiteLog in to forum 
Warning: Make sure you scan the downloaded attachment with updated antivirus tools  before opening them. They may contain viruses.
Use online scanners
here and here to upload downloaded attachment to check for safety.

Casting in two different grades of concrete

 
Post new topicReply to topic Thank Post    www.sefindia.org Forum Index -> Speak Out Box
View previous topic :: View next topic  
Author Message
sspawar
...
...


Joined: 05 Jun 2009
Posts: 1205

PostPosted: Thu Aug 04, 2022 11:03 am    Post subject: Casting in two different grades of concrete Reply with quote

Dear Sefians,


What is the best economic and quality controlled method to cast numerous columns' and beams' joints where the grade of concrete of Beam is if M30 and columns continue for upper floors of M40?

There is heavy reinforcement in columns and beams.


Best Regards
Back to top
View user's profile Send private message
vikram.jeet
General Sponsor
General Sponsor


Joined: 26 Jan 2003
Posts: 3903

PostPosted: Sat Aug 06, 2022 3:40 pm    Post subject: Reply with quote

Past Discussion on this is reproduced hereinunder :
aksharmacpwd wrote:
Dear All,

The practice being followed in CPWD is shared with SEFI community:
1. Provide specified concrete mix (i.e. richer mix) at column location.
2. This richer mix also simultaneously laid upto twice beam depth from column face .
3. Richer mix concrete was manufactured and laid prior to manufacture of lower grade concrete.
This is what we used to specify in structural drawings and also execute at site.

Anil K Sharma

--- On Fri, 10/17/08, vikram.jeet <forum@sefindia.org> wrote:

Quote:
From: vikram.jeet <forum@sefindia.org>
Subject: [SEFI] Re: Concerte grade at beam-column jucntion
To: general@sefindia.org
Date: Friday, October 17, 2008, 1:03 PM

Concrete at beam column junction

I think we may not encourage the site to use a lower mix
at the junction. Approach of using the column mix(higher mix) at
junction will be appropriate. A higher mix (of column) could be
prepared first and junctions could be filled in the begining of
concreting. In high rise constructions the differential in column
mixes vs Beam /slabsMix will always be there being dictated by
the design requirements

Regards

vikramjeet







__________________________________________________
Do You Yahoo!?
Tired of spam? Yahoo! Mail has the best spam protection around
http://mail.yahoo.com

Posted via Email
Back to top
View user's profile Send private message
sspawar
...
...


Joined: 05 Jun 2009
Posts: 1205

PostPosted: Sun Aug 07, 2022 6:58 am    Post subject: Reply with quote

Dear Sir,
I found a You tube upload related to this topic, have a very deep, study over, touched many aspects in that regards. Have a look, hope will get some information extra ordinary.
Regards



https://youtu.be/c3kU-nKy5OQ
Back to top
View user's profile Send private message
Display posts from previous:   
Post new topicReply to topic Thank Post    www.sefindia.org Forum Index -> Speak Out Box All times are GMT
Page 1 of 1

 

 
Jump to:  
You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot vote in polls in this forum
You cannot attach files in this forum
You can download files in this forum


© 2003, 2008 SEFINDIA, Indian Domain Registration
Publishing or acceptance of an advertisement is neither a guarantee nor endorsement of the advertiser's product or service. advertisement policy