View previous topic :: View next topic |
Author |
Message |
sspawar ...
Joined: 05 Jun 2009 Posts: 1205
|
Posted: Thu Nov 11, 2021 12:53 pm Post subject: what should be the maximum time for removal (stripping time) of shuttering |
|
|
Dear Sefians,
Minimum time for stripping out of shuttering is well described in codes and specifications.
But is there any restriction for longer time of shuttering enveloped the concrete elements like column beam slab foundation etc.
At many incidences shuttering are not removed till longer periods.
Curing of concrete will be affected or not.
If yes then what should be the limitations and norms.
Regards
S S Pawar |
|
Back to top |
|
|
vikram.jeet General Sponsor
Joined: 26 Jan 2003 Posts: 3903
|
Posted: Fri Nov 12, 2021 2:55 am Post subject: |
|
|
Generally rcc columns forms / rcc walls forms are removed after 24 - 48 hrs , even slip forms are moved after final set /24 hrs and curing is done for 14 days on concrete wrapped by Hessian cloth/gunny bags.
In case forms are kept longer , curing is still needed . Earlier wooden forms are are heat resistant and protect concrete from direct radiation of sun(keeping forms longer could be beneficial) , but summer months still need curing . In case of steel forms , no protection from rising day temperatures and keeping forms in position , will still require Hessians cloth to be kept moist nearby to forms in position to have cooling due to evaporation from cloth . The additional arrangement to hang cloths need to be provided and to be kept moist .
But it is seen that forms are struck early possible by construction agencies for reuse in upper lifts /floors .
For slab concrete , curing is effected from top thru ponding and keeping shuttering longer is immaterial . |
|
Back to top |
|
|
suraj General Sponsor
Joined: 17 Apr 2008 Posts: 5855 Location: NCR Faridabad, E mail suraj_engineer@yahoo.co.uk
|
Posted: Sun Nov 14, 2021 8:55 am Post subject: Curing |
|
|
Keeping forms in position for more than required time does not pose any problem to an extent temperature of concrete vicinity is maintained, between 20 to 27 deg Celcius
As, rightly stated by other expert engineer, about when evaporation is reduced by such arrangement of no exposition of concrete to weather directly, but only exposed area be formally cured
In fact, indirectly, instead of water curing, thermal curing to some extent is effected
In higher temperature zone, water sprinkling can be done on forms itself & direct water applied on exposed surfaces
If evaporation is prevented by whatever means, it is an automatic type of thermally induced curing
Formally, on certain massive blocks, no formal water curing is permitted, but only thermal curing for a couple of days, till surface can accept application of curing compound
Steam curing is also, conducted in certain pre-casting yards
we must think beyond old specifications, included within codes & other virtually, obsolete documents
On columns & wall surfaces, water evaporation is prevented by forming a vertical membrane of curing compound wax based or water based
Moreover, when GGBS / PFA etc. being used, curing requires extended time, for it impacts on normal setting of concrete, but in long run, ultimate strength remains same |
|
Back to top |
|
|
suraj General Sponsor
Joined: 17 Apr 2008 Posts: 5855 Location: NCR Faridabad, E mail suraj_engineer@yahoo.co.uk
|
Posted: Sun Nov 14, 2021 8:57 am Post subject: Field Engineering Building+General+FIDICSilver-Quality+Engineering discipline |
|
|
World
Buildings Practice Facilities Plants/Petrochemicals
Chapter 22
Project Execution Method EPC 225 MW Combined Cycle Power Project
Owner:
Project Execution Method-(Project Implementation Strategy)-Civil, Buildings & Plant Installations-An Overview
1 Document for General / Specific Directives for EPC Contractor, Subcontractors,
2 Design Engineers & Project Organisation Managers & Informative to Employer & Engineer
3 In Compliance to Article
. EPC Contract
EPC Contractor
.
https://www.facebook.com/pesuraj/posts/5271973676152094 Part 01 |
|
Back to top |
|
|
vikram.jeet General Sponsor
Joined: 26 Jan 2003 Posts: 3903
|
Posted: Sun Nov 14, 2021 9:23 am Post subject: |
|
|
Yes , very rightly reminded by Sri Suraj saheb , the removal of shuttering time prescribed in IS 456 is for OPC , but now a days PPC is being used ,for which longer period is needed for Strickling the shuttering /scaffolding. Strength gain is comparatively slow in PPC , though final strength is same. |
|
Back to top |
|
|
|
|
You cannot post new topics in this forum You cannot reply to topics in this forum You cannot edit your posts in this forum You cannot delete your posts in this forum You cannot vote in polls in this forum You cannot attach files in this forum You can download files in this forum
|
|
|