abhilashjoy SEFI Member

Joined: 26 Jan 2003 Posts: 3
|
Posted: Tue Dec 19, 2006 7:32 am Post subject: problem in placing of column & footin |
|
|
Hai Kasturi,
Abandon the bore well, Fill the bore well with sand and fill water to compact the sand. Construct the footing in the given location.
Regards
Abhilash
On Mon Dec 11 22:19:47 2006, kasturi1976[AT]yah... < kasturi1976[AT]yah...> wrote:
Quote: | hi, Iam designing a G+3 floor building.Iam facing a problem in placing of column & footing.Here the borewell position is fixed and it is at a distance of 1feet 3 inches away fom column face. Now the architect is asking to place the footing such that it covers the borewell from all sides.There is no chance to make footing eccentric. Architect argument is that once the footing is cast there are no chances of removal of casing pipe and it does not affect the location.
Can u suggest is this possible.
Find out what India is talking about on - Yahoo! Answers India Send FREE SMS to your friend's mobile from Yahoo! Messenger Version 8. Get it NOW
(
|
Posted via Email |
|
Back to top |
|
 |
|
|
You cannot post new topics in this forum You cannot reply to topics in this forum You cannot edit your posts in this forum You cannot delete your posts in this forum You cannot vote in polls in this forum You can attach files in this forum You can download files in this forum
|
|
|
|